Study
6.
Extricate client from PRP Group on Puente
Valley Superfund Site.
Objective. To extricate client from PRP Group
on Puente Valley Superfund Site .
Site Information:
 |
Site
previously used chlorinated solvents.
|
 |
Soils were
remediated.
|
 |
Chlorinated
solvents detected in groundwater beneath the site.
|
 |
Groundwater
at >70ft bgs.
|
 |
Site named
to PRP Group with $2.7 million plus in allocated costs to our client. |
Sampling Strategy
 |
Evaluated
site-specific and regional groundwater contaminant plumes.
|
 |
Performed
chemical fingerprinting of site chemicals and regional contaminants (all
chlorinated solvents).
|
 |
Evaluated
residual mass in vadose zone beneath the site.
|
 |
Evaluated
efficiency of onsite remediation system. |
Results
 |
Demonstrated
that the groundwater contamination beneath our client's property was not part
of the regional contaminant plume, even though it had some of the same
chemicals.
|
 |
Demonstrated
that the onsite contamination had been successfully cleaned up.
|
 |
RWQCB
concurred and issued a No Further Action Letter.
|
 |
The "No
Further Action" letter and our report were used to negotiate a de minimus cash out settlement
for our client with USEPA Region IX. |